Today did a site inspection of work at #GokhaleBridge with @mybmc & @WesternRlyofficials as well as both contractors.
The Gokhale bridge update is as follows:
-Work of demolition of bridge on railway tracks is in progress by railway contractor in 4 phases
-The first phase is complete and the entire work is targeted to be complete by 20th March.
-The BMC contractor has started work fabrication and will start work on site after the railway demolition work is over.
-They will take max 3 months to start traffic on one side once they start. Trying to squeeze it into 2 months so that we start one side of traffic in June.